Tunnels

IH 635 and Greenville Avenue
IH 635 and Greenville Avenue 1000 750 Southland Holdings

Completed in 2001 by Southland Contracting, the IH 635 and Greenville Avenue Project consisted of installing approximately 635 linear feet of 42-inch steel casing pipe by boring method. Project Details…

read more
M390 DOE#1840
M390 DOE#1840 1000 750 Southland Holdings

Completed in 2001 by Southland Contracting, the M390 DOE#1840 Project consisted of installing approximately 1,030 linear feet of 42-inch by Tunnel Boring Machine (TBM), approximately 2,457 linear feet of 36-inch…

read more
I35 & TXU Substation Repairs
I35 & TXU Substation Repairs 1000 750 Southland Holdings

Completed in 2001 by Southland Contracting, the I35 & TXU Substation Repairs Project consisted of repairing electrical conduit between Highline/Continental. Project Details Owner: TXU Electric Location: Texas, United States Performed…

read more
Murdock Lift Station Sewer Relief Line
Murdock Lift Station Sewer Relief Line 1000 750 Southland Holdings

Completed in 2001 by Southland Contracting, the Murdock Lift Station Sewer Relief Line Project consisted of installing approximately 480 linear feet of 22-inch High Density Polyethylene pipe (HDPE) by bore…

read more
C1C4B Group 6 Part 2 Contract 2
C1C4B Group 6 Part 2 Contract 2 1000 750 Southland Holdings

Completed in 2000 by Southland Contracting, the C1C4B Group 6 Part 2 Contract 2 Project consisted of installing approximately 200 linear feet of 8-inch, 30 linear feet of 18-inch, 1,948…

read more
Fort Worth Transportation Storm Sewer Main 390 Rehab
Fort Worth Transportation Storm Sewer Main 390 Rehab 1000 750 Southland Holdings

Completed in 2000 by Southland Contracting, the Fort Worth Transportation Storm Sewer Main 390 Rehab Project consisted of installing approximately 240 linear feet of 108-inch by Tunnel Boring Machine (TBM).…

read more
M207R G5, C3, P6, US DOE#2370
M207R G5, C3, P6, US DOE#2370 1000 750 Southland Holdings

Completed in 2000 by Southland Contracting, the M207R G5, C3, P6, US DOE#2370 Project consisted of installing approximately 1,247 linear feet of 12-inch sanitary sewer by Tunnel Boring Machine (TBM).…

read more
Dallas Water Meandering Way
Dallas Water Meandering Way 1000 750 Southland Holdings

Tunnel Boring Machine Project Details Owner: City of Dallas Location: Dallas, Texas, United States Performed as: Southland Contracting, Inc. Project value: xx Completion Date: April 2000

read more
Main C1C4B, G6, C2, P4, DOE#2719
Main C1C4B, G6, C2, P4, DOE#2719 1000 750 Southland Holdings

Completed in 2000 by Southland Contracting, the Main C1C4B, G6, C2, P4, DOE#2719 Project consisted of installing approximately 700 linear feet of 18-inch Class 51 Ductile Iron Pipe (DIP) by…

read more
TSU/SWB/MCI/TCI Coit Road @ IH635
TSU/SWB/MCI/TCI Coit Road @ IH635 1000 750 Southland Holdings

Completed in 2001 by Southland Contracting, the TSU/SWB/MCI/TCI Coit Road at IH635 Project consisted of installing approximately 610 linear feet of 72-inch bore by Tunnel Boring Machine (TBM). Project Details…

read more