Facilities

South Interceptor Force Main Project – Section A and Section B
South Interceptor Force Main Project – Section A and Section B 1000 750 Southland Holdings

Completed in 2015 by Oscar Renda Contracting, the South Interceptor Force Main Project – Section A and Section B Project consisted of two sections. Section A consists of 20-inch, 36-inch,…

read more
Phase V West Ashley Sewer Tunnel and Influent Pump Station
Phase V West Ashley Sewer Tunnel and Influent Pump Station 1000 750 Southland Holdings

Completed in 2020 by Oscar Renda Contracting, the Phase V West Ashley Sewer Tunnel and Influent Pump Station Project involved constructing a 60 MGD capacity influent pump station with a…

read more
Elm Fork Relief Interceptor EF, Phase 2A – Lift Station No. 1 Replacement
Elm Fork Relief Interceptor EF, Phase 2A – Lift Station No. 1 Replacement 1000 750 Southland Holdings

Completed in 2020 by Oscar Renda Contracting, the Elm Fork Relief Interceptor EF, Phase 2A – Lift Station No. 1 Replacement Project involved constructing a new 20.5 MGD capacity submersible…

read more
Navajo Gallup Water Supply Project, San Juan Lateral Block 9-11
Navajo Gallup Water Supply Project, San Juan Lateral Block 9-11 1000 750 Southland Holdings

Completed in 2020 by Oscar Renda Contracting, the Navajo Gallup Water Supply Project, San Juan Lateral Block 9-11 Project consisted of 28 miles of 48 and 42-inch diameter water transmission…

read more
East Side WTP Biological Filtration Optimization Improvements
East Side WTP Biological Filtration Optimization Improvements 1000 750 Southland Holdings

Completed in 2024 by Oscar Renda Contracting, the East Side WTP Biological Filtration Optimization Improvements Project consisted of constructing a backwash pump station, an electrical building, a hydrogen peroxide building,…

read more
Capers Ridge Pump Station and Raw Water Intake: Luce Bayou Interbasin Transfer Project
Capers Ridge Pump Station and Raw Water Intake: Luce Bayou Interbasin Transfer Project 1000 750 Southland Holdings

Completed in 2023 by Oscar Renda Contracting, the Capers Ridge Pump Station and Raw Water Intake: Luce Bayou Interbasin Transfer Project consisted of constructing the main intake structure that consisted…

read more