ICTF Rail Bridge
ICTF Rail Bridge 1000 750 Southland Holdings

Completed in 2014 by American Bridge, the ICTF Rail Bridge project involved constructing a 1,225′ railroad bridge with 24″ concrete piles, cast-in-place caps, precast beams, and a cast-in-place deck. The…

read more
Bridge No. 30 US 421 over Snow Cut Phases 1, 2, & 3
Bridge No. 30 US 421 over Snow Cut Phases 1, 2, & 3 1000 750 Southland Holdings

Completed in 2013 by American Bridge, the Bridge No. 30 US 421 over Snow Cut Phases 1, 2, & 3 project involved rehabilitating a 2,060′ bridge in Wilmington, NC. The…

read more
Miscellaneous Structural Improvements at the Robert F. Kennedy Bridge
Miscellaneous Structural Improvements at the Robert F. Kennedy Bridge 1000 750 Southland Holdings

Structural Improvements Project Details Owner: MTA Bridges & Tunnels Location: New York, New York, United States Performed as: American Bridge Company Project value: $53,947,713.00 Completion Date: February 2017

read more
Bonner Bridge Scour Protection
Bonner Bridge Scour Protection 1000 750 Southland Holdings

Completed in 2012 by American Bridge, the Bonner Bridge Scour Protection project involved installing a crutch bent and placing gabion baskets and sandbags around four existing bents to protect the…

read more
US 69 Missouri River Bridge
US 69 Missouri River Bridge 1000 750 Southland Holdings

Completed in 2017 by American Bridge, the US 69 Missouri River Bridge project involved replacing two parallel truss bridges near Kansas City, MO, built in 1935 and 1957. The new…

read more
Viceroy Anguilla – Coastal Protection
Viceroy Anguilla – Coastal Protection 1000 750 Southland Holdings

Completed in 2016 by American Bridge the Viceroy Anguilla – Coastal Protection project consisted of miscellaneous structural steel repairs. Project Details Owner: Louisiana Department of Transportation and Development Location: Baton…

read more
Horseshoe Arch Pedestrian Bridges
Horseshoe Arch Pedestrian Bridges 1000 750 Southland Holdings

Completed in 2017, the Horseshoe Arch Pedestrian Bridges project in Dallas, Texas, involved American Bridge supplying and erecting the structural steel components, including the arch, superstructure, and cables for twin…

read more
Woodrow Wilson Bridge – Bascule Span
Woodrow Wilson Bridge – Bascule Span 1000 750 Southland Holdings

ABCo lead JV bridge replacement project that involved complete construction (excluding foundations) of double leaf bascule drawbridge. Scope of work included steel plate girders and floor beams with cast-in-place 7.5-inch…

read more
M48 Severn Bridge Main Cable Inspection
M48 Severn Bridge Main Cable Inspection 1000 750 Southland Holdings

Completed in 2016, the M48 Severn Bridge Main Cable Inspection project involved providing access and project management for inspecting eight main cable panels on the 1960s suspension bridge. Work included…

read more
Three Nations Bridge (North Channel)
Three Nations Bridge (North Channel) 1000 750 Southland Holdings

Completed in 2011, the Three Nations Bridge (North Channel) project was the first of four phases replacing the existing bridge. It involved constructing three in-river piers with two 8’ drilled…

read more