WWTP Modifications & Improvements, Contract 1: Gravity Sewers, Tunnel & Lift Station

Completed in 2012 by Oscar Renda Contracting, the WWTP Modifications & Improvements, Contract 1: Gravity Sewers, Tunnel & Lift Station Project consisted of the installation of approximately 600 linear feet of 36-inch, 810 linear feet of 48-inch, 85 linear feet of 60-inch gravity sewer pipeline with manholes and related appurtenances. Approximately 1,700 linear feet of tunnel with 60-inch carrier pipe. Construction of screw pump lift station structure, paving, and site restoration.

Project Details

  • Owner: City of Batesville
  • Location: Batesville, Arkansas, United States
  • Performed as: Oscar Renda Contracting, Inc.
  • Project value: $5,606,000.00
  • Completion Date: August 2012