Completed in 2000 by Southland Contracting, the West Fork Relief Interceptor Project consisted of installing approximately 147 linear feet of 119-inch clear inside diameter tunnel liner by the tunneling method to include digging, shoring the pits, furnishing and installing liner plate, rail, grout invert, and pea gravel.
Project Details
- Owner: Trinity River Authority
- Location: Arlington, Texas, United States
- Performed as: Southland Contracting, Inc.
- Project value: $137,445.00
- Completion Date: August 2000