Completed in 2009 by Southland Contracting, the West Fork Relief Interceptor Project consisted of installing approximately 265 linear feet of 102-inch tunnel, 750 linear feet of 96-inch tunnel, and 703 linear feet of 90-inch tunnel. All of the tunnels will be installed using a two-pass method with liner plate as the primary liner.
Project Details
- Owner: Trinity River Authority
- Location: Grand Prairie, Texas, United States
- Performed as: Southland Contracting, Inc.
- Project value: $1,822,824.00
- Completion Date: November 2009