Completed in 2005 by Southland Contracting, the West Bouldin Creek Wastewater Phase A2 Project consisted of installing approximately 2,759 linear feet of 50-inch tunnel for 24-inch wastewater line. This tunnel was a serpentine tunnel cut by Tunnel Boring Machine (TBM). The serpentine tunnel was required due to two 500 radius curves.
Project Details
- Owner: City of Austin
- Location: Austin, Texas, United States
- Performed as: Southland Contracting, Inc.
- Project value: $2,828,576.00
- Completion Date: December 2005