Southwest Contract No. 5

Completed in 1988 by Mole Constructors, the Southwest Contract No. 5 project involved the construction of about 6,800 linear feet of 131-inch tunnel using a modified Lovat 126-inch/131-inch Tunnel Boring Machine. Excavation occurred through shale at a depth of 110 feet.

Project Details

  • Owner: Northeast Ohio Regional Sewer District
  • Location: Cleveland, Ohio, United States
  • Performed as: Mole Constructors, Inc.
  • Project value: $8,628,660.00
  • Completion Date: 1988