Southside II Water Transmission Main Part 2

Completed in 2008 by Oscar Renda Contracting, the Southside II Water Transmission Main Part 2 project consisted of approximately 8,105 linear feet of 54-inch pipe, 30 linear feet of 24-inch, 640 linear feet of 78-inch casing pipe by tunneling for railroad crossing, manholes and related appurtenances, asphalt paving, cathodic protection and site restoration. Pigging method was utilized for pipeline cleaning. Traffic control, barricades and flagging service for all work associated within the roadways and railroad crossings.

Project Details

  • Owner: City of Fort Worth
  • Location: Fort Worth, Texas, United States
  • Performed as: Oscar Renda Contracting, Inc.
  • Project value: $4,360,233.00
  • Completion Date: December 2008