Completed in 1987 by Oscar Renda Contracting, the Southside Division Sanitary and Sludge project consisted of the installation of approximately 5,900 linear feet of 120-inch reinforced concrete cylinder pipe (RCCP), 240 linear feet of 72-inch RCCP, 11,800 linear feet of 10-inch sewer force, 130 linear feet of 18-inch sewer force main, rehabilitation of sludge gates and junction boxes.
Project Details
- Owner: City of Dallas
- Location: Dallas, Texas, United States
- Performed as: Oscar Renda Contracting, Inc.
- Project value: $3,879,160.00
- Completion Date: November 1987