Completed in 2011 by Oscar Renda Contracting, the South Main Street and Wintergreen Road, Paving, Drainage and Water Lines project consisted of the installation of approximately 2,300 linear feet of 96-inch Pre-stressed Concrete Cylinder Pipe (PCCP) waterline, 550 linear feet of 96-inch PCCP waterline by bore, 2,500 linear feet of 30-inch PCCP waterline. Approximately 22,640 square yards of 8-inch street concrete paving with lime stabilization base on Wintergreen Road. Removal and replacement of concrete paving.

Project Details

  • Owner: City of Duncunville
  • Location: Duncanville, Texas, United States
  • Performed as: Oscar Renda Contracting, Inc.
  • Project value: $7,467,776.00
  • Completion Date: 2011