Completed in 2003 by Southland Contracting, the South Lubbock Drainage Improvement Project consisted of installing approximately 12,100 linear feet of 72-inch internal diameter (ID) Hobas sewer pipe using two pass tunnel lining. The project also involved the excavation of 622 linear feet of 60-inch tunnel, 603 linear feet of 48-inch tunnel and 625 linear feet of 42-inch tunnel. Portions of rock had a compressive strength ranging to 17,000 psi. Groundwater varied between 20 to 400 gallons per minute.
Project Details
- Owner: City of Lubbock
- Location: Lubbock, Texas, United States
- Performed as: Southland Contracting, Inc.
- Project value: $9,284,172.00
- Completion Date: April 2003