Norfolk Southern Railway Bridge Relocation

Completed in 1994 by American Bridge, the Norfolk Southern railway bridge relocation project involved removing a 409-foot, 1,500-ton vertical lift span from Florence, AL, and relocating it to Hannibal, MO. The truss was reassembled on barges and falsework. During a three-day outage, the existing swing span was replaced, widening the navigation clearance by several hundred feet. The project also included installing new operating machinery and electrical systems.

Project Details

  • Owner: Norfolk Southern Railroad (NS Rail)
  • Location: Hannibal, Missouri, United States
  • Performed as: American Bridge Company
  • Project value: $9,594,834.00
  • Completion Date: April 1994