Montana East 36-inch Waterline Extension, Phase 2

Completed in 2024 by Oscar Renda Contracting, the Montana East 36-inch Waterline Extension, Phase II project consisted of 36-inch waterline extension located along Homestead Ranchos Real PS to Edgemere. Scope of work included installation of 7,100 linear feet of 36-inch concrete steel cylinder waterline, 5,350 linear feet of 42-inch HDPE waterline, two 6-inch air release valves, one 8-inch air release valve, two 6-inch blow off valves, seven 36-inch gate valves, six 42-inch gate valves, 28,000 square yards of 2-inch HMAC, and 1,040 cubic yards of 12-inch 2-SAC.

Project Details

  • Owner: El Paso Water Utilities
  • Location: El Paso, Texas, United States
  • Performed as: Oscar Renda Contracting, Inc.
  • Project value: $13,052,589.00
  • Completion Date: July 2024