Completed in 2003 by Southland Contracting, the MC-4A Parallel Interceptor Rehabilitation Project – Joe Pool Lake Project consisted of installing approximately 75 foot by 45 foot shaft with a depth of 55 foot, 420 linear feet of 54-inch gravity sewer line by other than open cut, and 170 linear feet of 66-inch by 0.875 wall steel casing for Hobas pipe.

Project Details

  • Owner: Trinity River Authority
  • Location: Grand Prairie, Texas, United States
  • Performed as: Southland Contracting, Inc.
  • Project value: $378,600.00
  • Completion Date: January 2003