Completed in 2016, the M48 Severn Bridge Main Cable Inspection project involved providing access and project management for inspecting eight main cable panels on the 1960s suspension bridge. Work included wire wrap removal, lead paste application, wedging, sampling, re-compaction, re-wrapping, and re-enabling the dehumidification system.
Project Details
- Owner: Severn River Crossing PLC
- Location: South West, England, United Kingdom
- Performed as: American Bridge Company
- Project value: $4,278,487.00
- Completion Date: January 2018