Completed in 2015 by Oscar Renda Contracting, the Section 15-1 of the Integrated Pipeline Project consisted of approximately 25,479 linear feet of 108-inch water line by combination of open-cut and tunneling. Installation of valves, manholes and related appurtenances. Removal and replacement of asphalt and gravel roads along water line alignment. Construction of driveways, permanent steel gates, barb wire fencing, concrete cable mats at all streams crossings. Construction of interconnect structure to include mechanical, structural, fiber optics, electrical and instrumentation/SCADA. Scope of work included, clearing, grading, excavation, pipeline installation, rip rap placement, and final restoration.
Project Details
- Owner: Tarrant Regional Water District
- Location: Corsicana, Texas, United States
- Performed as: Oscar Renda Contracting, Inc.
- Project value: $26,374,698.00
- Completion Date: December 2015