Completed in 1992 by Mole Constructors, the Hilltop Interceptor Contract H-2 project involved roughly 18,000 linear feet of tunnel for 60-inch and 66-inch concrete pipes. Excavation was carried out through shale rock at depths varying from 150 feet to 180 feet.

Project Details

  • Owner: Northeast Ohio Regional Sewer District
  • Location: Cleveland, Ohio, United States
  • Performed as: Mole Constructors, Inc.
  • Project value: $9,242,000.00
  • Completion Date: 1992