Hickory Water Supply Project Transmission Main

Completed in 2013 by Oscar Renda Contracting, the Hickory Water Supply Project Transmission Main Project consisted of the installation of approximately 316,800 linear feet of 30-inch C303 bar-wrapped concrete cylinder water transmission main from Melvin well field to Avenue K in San Angelo, TX. Installation of manholes, and related appurtenances. Traffic control, flagging service for work associated within the city streets. Site restoration included asphalt paving, fencing and general site restoration. Scope of work included, clearing, grading, excavation for pipeline installation, structural concrete placement, and final restoration.

Project Details

  • Owner: City of San Angelo
  • Location: San Angelo, Texas, United States
  • Performed as: Oscar Renda Contracting, Inc.
  • Project value: $39,000,000.00
  • Completion Date: September 2013