Freeport Harbour Berths 3, 8, & 9 Refurbishment

Completed in 2015, the Freeport Harbour Berths 3, 8, & 9 Refurbishment project involved demolishing existing facilities and installing new bulkhead systems—204m at Berth 3 and 152m at Berths 8 and 9. The work included sheet pile walls, tiebacks, concrete encapsulation, bollards, fenders, minimal dredging, and backfill/paving behind the new structures.

Project Details

  • Owner: Freeport Harbour Company, Ltd.
  • Location: Freeport Grand, City of Freeport, Bahamas
  • Performed as: American Bridge Company
  • Project value: $16,534,659.00
  • Completion Date: December 2017