Completed in 2002 by Oscar Renda Contracting, the Entergy Power Group Transmission Line project was a Fast Track Design Build Project with Winn Engineers, consisting of Installing a Pump Station and 143,000 linear feet of 20-inch ductile iron pipe and HDPE for power plant. Project was built and in service in 4 months. Soil conditions were wet sand, sandy clay and cemented sands.
Project Details
- Owner: Energy Power Group
- Location: Longview, Texas, United States
- Performed as: Oscar Renda Contracting, Inc.
- Project value: $9,300,000.00
- Delivery Model: Design-Build
- Completion Date: September 2002