Druid Lake Finished Reservoir Water Tanks

Completed in 2024 by Oscar Renda Contracting, the Druid Lake Finished Water Tanks project consisted of water tank construction and miscellaneous site restoration and development. Scope of work includes constructing two concrete water tanks (400-foot and 550-foot diameter precast, prestressed concrete tanks), installation of 6,000 LF of 72-inch diameter waterline, valves and related appurtenances, decommissioning of existing druid effluent chlorination station, installation of new diffused aeration system, new park/recreational facility, and landscaping.

Project Details

  • Owner: City of Baltimore
  • Location: Baltimore, Maryland, United States
  • Performed as: Oscar Renda Contracting, Inc.
  • Project value: $148,261,555.00
  • Completion Date: November 2024