Dearborn Center

Completed in 2001 by American Bridge, the Dearborn Center project involved the fabrication and erection of structural steel for a 37-story, 1,500,000 SF office building in Chicago, standing 518′ high. The project utilized large 55,000 SF floorplates with a steel-framed core. Erection was done using two AB-owned tower cranes, starting in October 2000 and finishing in December 2001. The structural steel weighed 15,000 tons.

Project Details

  • Owner: Douglas Elliman Beitler Company
  • Location: Chicago, Illinois, United States
  • Performed as: American Bridge Company
  • Project value: $8,248,644.00
  • Completion Date: December 2001