Crabtree Basin Wastewater System Conveyance Improvements, Phase 2

Completed in 2022 by Oscar Renda Contracting, the Crabtree Basin Wastewater System Conveyance Improvements, Phase 2 Project consisted of the installation of 25,000 linear feet of 36-inch and 54-inch gravity sewer by open cut – 7 open cut crossings of Crabtree Creek and several open cut crossings of smaller tributaries to Crabtree Creek. Additional work included constructing 82 precast manholes, junction boxes and related appurtenances, rehabilitation of three inverted siphons at Crabtree Creek (including all line), concrete repair and bypass pumping, and site improvements (cleanup and restoration).

Project Details

  • Owner: City of Raleigh
  • Location: Raleigh, North Carolina, United States
  • Performed as: Oscar Renda Contracting, Inc.
  • Project value: $20,009,819.00
  • Completion Date: July 2022