Coosa River Bridge

This project involved the overall maintenance and access improvements, suspender adjustment and support for structural testing of gas pipe. The mainspan is 700′. The work included: replacement of handrail cable system, installation of ladders and railings on bridge towers, adjustment of suspenders to correct the bridge’s profile, replacement and tightening of various fittings and bolts and monitoring the geometry of the entire structure during hydro-testing.

Project Details

  • Owner: Transcontinental Gas Pipe Line Company, LLC.
  • Location: Clanton, Alabama, United States
  • Performed as: American Bridge Company
  • Project value: $2,227,465.00
  • Completion Date: March 2011