Completed in 2018 by Oscar Renda Contracting, the Central WWTP Existing Peak Flow Basins Rehabilitation Project consisted of the removal and replacement of existing combined berm. Scope of work included improvements to basin floor slabs, improvements to Chlorine contact basin effluent diversion to basin A, and installation of 66-inch forcemain from existing pump station to Basin-B-2 and Basin A. Additional work included extension of wet well wall at Peak Flow Pump Station, electrical and instrumentation modifications to existing facilities, and construction of access road to basin B-1.
Project Details
- Owner: City of Dallas
- Location: Dallas, Texas, United States
- Performed as: Oscar Renda Contracting, Inc.
- Project value: $8,675,000.00
- Completion Date: March 2018