Completed in 2007, the Celebration Wetlands Area Mitigation Area 18.7A Infill project consisted of the site revitalization that included site demolition; mass clearing & grubbing; erosion/sedimentation control; mass de-mucking; dewatering; sheet pile; mass import; sodding & seeding. This project had the removal of 40,000 cubic yards of muck and replaced with 60,000 cubic yards of embankment in 4 months. The project was completed 30 days earlier than scheduled.
Project Details
- Owner: The Celebration Company
- Location: Kissimmee, Florida, United States
- Performed as: Johnson Bros. Corporation
- Project value: $1,470,519.00
- Completion Date: August 2007