Castroville Rd. / SW 38th Street Lift Station

Completed in 2005 by Oscar Renda Contracting, the Castroville Rd. / SW 38th Street Lift Station project consisted of the construction of a 3-million gallon per day lift station, which includes a cast-in-place concrete wet well and valve vault structures, manhole structures, 6-inch thru 18-inch influent discharge, sewer force main and gravity sewer piping, valves and appurtenances, submersible wastewater pumps, HVAC system, associated electrical and instrumentation improvements. Project was finished 4 months early.

Project Details

  • Owner: San Antonio Water Systems
  • Location: San Antonio, Texas, United States
  • Performed as: Oscar Renda Contracting, Inc.
  • Project value: $2,849,550.00
  • Completion Date: August 2005