C-13 Broadway Corridor, Package B

Completed in 2019 by Oscar Renda Contracting, the C-13 Broadway Corridor, Package B Project consisted of open cut sewer main installation that consisted of 350 linear feet of 24-inch, 3,700 linear feet of 36-inch, 1,500 linear feet of 42-inch, and 84 linear feet of 60-inch. Additional working included installation of 1,900 linear feet of 36-inch and 42-inch tunneling with and without casing, and rehabilitation of 7,000 linear feet of 60-inch existing gravity sewer by CIPP method.

Project Details

  • Owner: San Antonio Water Systems
  • Location: San Antonio, Texas, United States
  • Performed as: Oscar Renda Contracting, Inc.
  • Project value: $15,592,712.00
  • Completion Date: October 2019