Completed in 2005 by Oscar Renda Contracting, the Buffalo Creek Lift Station project consisted of the construction of a lift station, installation of 97 linear feet of 54-inch ductile iron pipe, installation of 720 linear feet of 48-inch PVC pipe. Installation of several manholes, landscaping and permanent fencing.
Project Details
- Owner: North Texas Municipal Water District
- Location: Forney, Texas, United States
- Performed as: Oscar Renda Contracting, Inc.
- Project value: $1,721,209.00
- Completion Date: April 2005