Completed in 2014 by Oscar Renda Contracting, the Briar Creek Relief Sewer Phase II Project consisted of the installation of approximately 4,235 linear feet of 54-inch and 3,265 linear feet of 48-inch sewer, 8,975 linear feet of 42-inch sewer, 1,418 linear feet of 8-inch to 36-inch sewer, 85 manholes, construction of 6 stream crossings and 4 tributary crossings and installation of 1,340 linear feet of untrenched tunnel. Removal and replacement of concrete trail at the golf course. Demolition of small building at the golf course. Scope of work included, clearing, grading, excavation for pipeline installation, structural concrete placement, rip rap placement and final restoration.
Project Details
- Owner: Charlotte Mecklenburg Utilities Department
- Location: Charlotte, North Carolina, United States
- Performed as: Oscar Renda Contracting, Inc.
- Project value: $17,634,280.00
- Completion Date: September 2014