Completed in 2004 by Johnson Bros. Corporation, the Biloxi I-10 shoulders project consisted of addition of lanes to 5 locations (10 bridges) on I-10, inside lanes of east and west bound bridges, add shoulders to 5 bridges. Drive piles, caps, concrete girders, steel tub girders, decks, MOT, repair existing bridge decks, caps, piling in some cases.
Project Details
- Owner: Mississippi Department of Transportation
- Location: Biloxi, Mississippi, United States
- Performed as: Johnson Bros. Corporation
- Project value: $13,052,853.00
- Completion Date: April 2004