Completed in 2003 by Southland Contracting, the Bear Creek Interceptor Sewer System Rehab Project consisted of installing approximately 14,383 linear feet of 54-inch Hobas pipe by other than open cut (OTOC) and approximately 2,138 linear feet of 36-inch cast-in-place pipe (CIPP).
Project Details
- Owner: Trinity River Authority
- Location: Arlington, Texas, United States
- Performed as: Southland Contracting, Inc.
- Project value: $3,439,316.00
- Completion Date: December 2003