Atoka Raw Water Pipeline

Completed in 2025 by Oscar Renda Contracting, the Atoka Raw Water Pipeline project consisted of approximately 69,827 linear feet of 72-inch welded steel water main and appurtenances. The scope of work included 1,027 linear feet of 96-inch tunnel for 72-inch steel welded pipe connection to existing 72-inch, installation of valves and blow-offs, hydraulic testing, street and driveway repairs, right-of-way restoration, and cleanup.

Project Details

  • Owner: Oklahoma City, Water Utilities
  • Location: Oklahoma City, Oklahoma, United States
  • Performed as: Oscar Renda Contracting, Inc.
  • Project value: $42,390,684.00
  • Completion Date: March 2025